PERI ASIA PTE LTD, Projects, Formwork, Scaffolding, Engineering - Assumption Pathway School Upgrading

Current Projects

PERI ASIA PTE LTD, Projects, Formwork, Scaffolding, Engineering - Assumption Pathway School Upgrading PERI ASIA PTE LTD, Projects, Formwork, Scaffolding, Engineering - Assumption Pathway School Upgrading PERI ASIA PTE LTD, Projects, Formwork, Scaffolding, Engineering - Assumption Pathway School Upgrading

Assumption Pathway School Upgrading




An upgrading project for Assumption Pathway School was started in May 2009 and involved the addition of a 5-storey block comprising of administration, teaching, dormitory, car parking and ancillary facilities at the Upper Bukit Timah site.

To get the job done cost-effectively and effciently, the contractor chose to use PERI's VARIO GT 24 Column formwork system for this project. The typical column had dimensions of 800mm x 600mm x 2.7m.

The project was completed in Feb 2011.

PERI Systems In Use
  • VARIO GT 24 Column formwork

  • Arnel Bulosan


    Site Quantity Surveyor, Fonda Construction Pte Ltd

    "We have used the VARIO GT 24 Column formwork system as it is easy to install, cost-effective and less manpower needed."

    Contractor: Fonda Construction Pte Ltd
    PERI Sales Engineer: Wong Joo Ben, HP 9794 8721
    PERI Formwork Instructor: Peter Faustino
    Field Service: PERI ASIA Pte. Ltd., Singapore